FAT evidence
Verifies supplied equipment and available functions before shipment under documented factory conditions.
- Scope and document review
- Available functional tests
- Deferred and simulated conditions
Test the agreed basis
Factory Acceptance Testing and Site Acceptance Testing answer different questions: FAT checks the available equipment and controls before shipment, while SAT checks the installed line against the agreed site, product, package and utility conditions.
Answer first
The plan should trace each accepted requirement to a test method, reference product or substitute medium, package material, measurement record, responsibility and open-point rule. FAT should verify what can genuinely be observed at the supplier location; SAT should address installed interfaces and conditions that could not be represented there, without treating either test as universal food-process validation.
Interactive acceptance basis
A deferred test is controlled only when the reason, owner, location, materials and closure rule are recorded.
Rows with a usable status0 / 8
Rows still needing clarification8 / 8
Emailing this worksheet gives the Allot Tech project desk a defined starting point. The reply can focus on missing inputs, the preliminary process-and-package route, scope interfaces and the next drawings or samples needed before a comparable quotation.
Selections stay in this browser unless you choose to copy or email the summary. Verify the project desk at allottech.com.
01 / Test basis
An acceptance test cannot resolve an undefined contract basis. The approved test plan should identify which product, package, output condition, materials, utilities and connected systems are available, then state how unavailable conditions will be handled.
02 / Factory acceptance
FAT can review equipment identity, workmanship observations, controls, interlocks, recipes, alarms, dry or wet functions and available package handling. The plan must disclose when upstream, downstream, utilities or actual product conditions are simulated or absent.
03 / Site acceptance
SAT begins only after site prerequisites and commissioning gates are met. It focuses on installed utilities, interconnecting pipework, actual line controls, product and container feed, downstream acceptance, operator access and the agreed reference operating condition.
04 / Closure
A test event is not complete merely because equipment has run. Results, deviations, configuration versions, corrective actions, conditional acceptance and remaining buyer or supplier tasks should be signed off through the project document process.
Acceptance matrix
A requirement may be fully testable at FAT, deferred to SAT or divided between both. The open-point rule prevents a limitation from being mistaken for a pass.
| Test area | FAT evidence | SAT evidence | Open-point rule |
|---|---|---|---|
| Scope and identity | Equipment, key components and document status against approved scope | Installed identity and connection against site drawings | Record substitutions, missing items and approval status |
| Package handling | Available reference containers, closures, labels and packs through factory setup | Actual materials through the installed infeed, filling and end of line | State which formats or materials remain untested |
| Process and filler feed | Available tanks, pumps, instruments and simulated or real feed conditions | Actual upstream transfer, utility and filler-inlet conditions | Do not treat substitute-medium behavior as final product proof |
| Controls and interlocks | Modes, alarms, recipes, permissives and simulated line handshakes | Real equipment communications and site fault or restart behavior | List every simulated signal and its later verification method |
| Complete-line behavior | Connected factory run only to the extent the offered setup permits | Installed module balance, accumulation and agreed operating sequence | Tie any performance conclusion to the exact test condition |
| Documents and training | Draft manuals, drawings, software records and test reports | As-built updates, training records and handover package | Keep acceptance conditional until required closure evidence is supplied |
Acceptance boundaries
Separating factory verification, site verification and product validation protects the buyer from conclusions that the observed test cannot support.
Verifies supplied equipment and available functions before shipment under documented factory conditions.
Verifies installation, real interfaces and the agreed line behavior after site commissioning prerequisites are complete.
Addresses product safety, process outcome or destination-specific requirements through separately qualified project work.
Test-plan inputs
When an input is unavailable, the plan should state the substitute, limitation and later verification point rather than silently reducing the test scope.
Illustrative acceptance plan
A carbonated PET line is assembled for FAT, but the buyer beverage and final site utility conditions are not available at the supplier location. Containers, closures and selected packaging materials are available.
Preliminary resultThe buyer receives useful pre-shipment evidence while preserving a clear list of conditions that only SAT or separate project validation can resolve.
Illustrative acceptance logic only. Actual test media, methods, criteria and responsibilities must be approved in project-specific documents.
Evidence boundary
Evidence labels keep a reference architecture separate from a final design or commercial promise.
The approved reference catalog supports the process, filling and packaging modules that may appear in a complete-line test boundary; it does not define universal acceptance criteria.
General commissioning and verification logic supports requirement traceability, documented test conditions, simulation disclosure and controlled punch-list closure.
The signed specification, approved FAT and SAT plans, site conditions, product information and witnessed records establish actual acceptance.
Buyer questions
These are planning answers. Final process and equipment choices require a confirmed project brief.
No. FAT covers functions and evidence available before shipment. SAT covers the installed system, actual site interfaces and agreed conditions that could not be represented at the factory.
Not by itself. A substitute medium can verify selected mechanical or control functions, but differences in product properties, temperature, carbonation, particles or hygiene conditions must remain explicit.
Complete-line acceptance should use the agreed reference product and package basis and verify system relationships, not simply collect unrelated maximum-speed demonstrations.
No. Product safety, shelf life and regulatory outcomes require their own qualified, product- and destination-specific validation and cannot be inferred from a machinery FAT or SAT.
Catalog reference The supplied 2026 catalog supports the named CSD and juice/tea equipment chains and is the source for the redrawn functional routes.
Engineering principle Interface explanations show why product, process, package, utilities and line balance must be reviewed together.
Project confirmation The routes are not a final process design, P&ID, validated cycle, quotation, availability statement or performance guarantee. Signed project documents define the final scope.