Beverage Bottling Line RFQ Checklist: Get a Comparable Quotation

A beverage bottling line RFQ should give every supplier the same product, process, package, output, factory and execution basis. “Send your best line” produces machine lists that look comparable but often have different boundaries.

Answer first

What information should a beverage bottling line RFQ include?

Include the beverage and recipe summary, preservation and filling route, approved container and closure drawings, label and secondary pack, output at one reference SKU, product schedule and changeovers, raw-water and utility information, factory layout and access, required supply limits, documentation, testing, installation, training and acceptance responsibilities. Mark unknowns openly and require each supplier to state assumptions, options and exclusions.

From requirement to decision

What does a useful beverage-line enquiry look like?

The two briefs below are fictional planning examples, not customer projects or validated processes. They show the level of detail that makes a first discussion useful. Replace the example quantities and leave genuinely unknown conditions marked “to be confirmed”; do not guess a thermal process or shelf-life guarantee.

Illustrative planning example — replace with your project’s verified basis
RFQ fieldExample A: carbonated soft drinkExample B: juice from concentrate
Product and starting pointFlavoured carbonated beverage prepared from water and syrup. Request preparation, mixing and carbonation.Juice drink blended from purchased concentrate. No fresh-fruit extraction requested; recipe, acidity and pulp specification pending.
Container and finished packPurchased 500 mL PET bottles with screw closures; 12-bottle packs. Bottle, neck and closure drawings to follow.Purchased 500 mL bottles and closures proposed for hot filling, subject to compatibility approval; secondary pack still to be selected.
Output basis40,000 saleable bottles per 8-hour scheduled shift. Ask for the supplier’s stated loss and changeover assumptions, not only filler BPH.20,000 saleable bottles per day; shift arrangement and SKU change frequency to be confirmed before equipment sizing.
Process conditions still openCO₂ target, recipe properties, inlet water quality and required utility conditions to be reviewed.Desired distribution is ambient. A qualified process review must determine whether hot fill is suitable and establish the preservation basis; no temperature or shelf life is assumed.
Requested supplier returnProcess flow, scope list, utilities, SKU-specific rates, interfaces, exclusions, test basis and itemized commercial offer.Preparation and preservation route, optional-module rationale, compatible package basis, stop/restart plan and scoped quotation.

What to attach to your actual enquiry

Send a product summary, available bottle/closure drawings, pack photograph or drawing, required saleable output and a site sketch if available. Include destination, existing equipment and the requested start/end of supply. A non-confidential recipe summary is sufficient for the initial discussion; do not send trade secrets until the appropriate arrangements are agreed.

What to ask for in the reply

Request one assumptions register showing confirmed, provisional and missing inputs; a process-to-pack flow; equipment and utility boundaries; output by SKU; and acceptance conditions. Ask suppliers to flag alternatives explicitly. This lets the buyer compare the same project instead of comparing differently scoped machine lists.

Discuss your own project with Mr Kcal at Allot Tech. The email link opens a blank project brief for you to edit; nothing is sent automatically.

Interactive RFQ readiness check

See which missing inputs will make quotations diverge.

A controlled “to be confirmed” is acceptable. The problem is an unstated assumption that each bidder resolves differently.

Decision areaWhat to controlCurrent status
Reference beverage Ingredients, known properties, carbonation, particles and preservation context.
Approved package Container, neck or end, closure, label, secondary pack and available drawings.
Usable output basis Reference SKU, good-output definition, production calendar and changeovers.
Process boundary Preparation, treatment, filling condition, post-fill route and CIP expectations.
Factory envelope Plan, dimensions, access, elevations, drains, logistics and retained equipment.
Utility basis Available qualities and conditions for power, water, air, heat, cooling and gases.
Responsibility matrix Included, optional, excluded, buyer-supplied and third-party work.
Controls + documentation Site standards, interfaces, drawings, manuals, backups and language needs.
FAT / SAT basis Reference materials, duration, measures, witness rules, deviations and retests.
Destination + schedule Country, delivery term, site-ready date and unresolved compliance questions.

Rows with a usable status0 / 10

Rows still needing clarification10 / 10

Use the first technical review to close the open rows.

Emailing this worksheet gives the Allot Tech project desk a defined starting point. The reply can focus on missing inputs, the preliminary process-and-package route, scope interfaces and the next drawings or samples needed before a comparable quotation.

Email My RFQ Gaps

Selections stay in this browser unless you choose to copy or email the summary. Verify the project desk at allottech.com.

01 / Technical basis

Describe one reference product and package completely

Select the SKU that will anchor process, speed and acceptance comparisons. Other beverages, bottle sizes, closures, labels and packs should be listed as additional formats with their own changeover and performance questions.

  • Recipe and product condition
  • Preservation and filler inlet basis
  • Container, closure, label and pack drawings
  • Reference rate and production schedule

02 / Factory and scope

Show where the supplier boundary begins and ends

Provide layout, floor and access information, utilities and local constraints. Ask each supplier to mark equipment, process piping, conveyors, controls, utility generation, installation, consumables and buyer-supplied work as included, optional or excluded.

  • Available space, height and material routes
  • Utility quality, pressure, flow and ownership
  • Equipment and interconnection boundary
  • Civil, local labor and permit responsibility

03 / Evidence and delivery

Define how the proposed line will be reviewed and accepted

The RFQ should request a process description, equipment list, utility schedule, layout, document register and schedule. FAT, shipment, installation, SAT, training, spares and open-item closure need explicit conditions and owners.

  • Proposal assumptions and exclusions
  • Drawings, calculations and document list
  • FAT and site acceptance basis
  • Training, spares and handover records

RFQ completeness check

Require the same response structure from every supplier

A quotation is comparable only when technical basis and scope status are visible.

RFQ blockBuyer suppliesSupplier returns
Product + processRecipe, condition and required routeProcess description, assumptions and equipment
Package + rateDrawings, pack and reference outputCompatibility, changeovers and performance basis
Factory + utilitiesLayout, access and available servicesLayout, load schedule and connection points
Commercial scopeRequired boundary and destinationIncluded, optional, excluded and buyer-supplied matrix
ExecutionRequired schedule and acceptance intentDocuments, FAT, delivery, installation, SAT and handover plan

Evidence boundary

What supports this guide—and what still needs confirmation.

Evidence labels keep a reference architecture separate from a final design or commercial promise.

Catalog reference

The supplied catalog supports reference equipment and process-chain discussion but does not replace a project RFQ or signed specification.

Engineering interpretation

A structured RFQ connects product, package, output, utilities, site, scope and acceptance into one comparison basis.

Project confirmation

Only the final signed technical and commercial documents establish supply, performance, price, schedule and responsibilities.

Buyer questions

Frequently asked questions

These are planning answers. Final process and equipment choices require a confirmed project brief.

Can an RFQ be based on bottles per hour only?

No. Rate must be tied to a product, fill condition, container, closure, label and pack, while preparation and downstream systems need the same reference basis.

Should unknown information be omitted?

No. Mark it as open and assign a confirmation owner and date. Hidden unknowns become incompatible assumptions in supplier quotations.

How many suppliers should receive the RFQ?

That is a commercial decision, but every invited supplier should receive the same revision-controlled basis so scope and evidence can be compared fairly.

How to read the technical evidence

Catalog reference The supplied 2026 catalog supports the named CSD and juice/tea equipment chains and is the source for the redrawn functional routes.

Engineering principle Interface explanations show why product, process, package, utilities and line balance must be reviewed together.

Project confirmation The routes are not a final process design, P&ID, validated cycle, quotation, availability statement or performance guarantee. Signed project documents define the final scope.